Oracle invokes 'force majeure' clause to avoid controversial data center project

PANews reported on September 24 that Oracle (ORCL.N) is trying to avoid the huge expenses incurred by building a large data center project in New Mexico, according to Bloomberg. This undoubtedly adds new variables to this project that has been plagued by opposition and regulatory obstacles.

Oracle has sent a notice to the project's developer, a unit of Blue Owl Capital, invoking a force majeure clause, according to people familiar with the matter. People familiar with the matter said Oracle is not trying to exit the project as an anchor tenant, but is hoping to defer related payments if the Project Jupiter data center project encounters delays and fails to come online as planned in 2028.

Похожие новости

  1. Маск: Операционные расходы Grok Bot несоизмеримо высоки по сравнению с его выручкой и не могут поддерживаться в долгосрочной перспективе.

    PANews, 2 ноября: В ответ на вопрос пользователя на платформе X о быстром исчерпании квот использования Grok Bot Маск заявил, что операционные издержки Grok Bot...

  2. China Merchants Bank и ряд других учреждений запустили в приложении цифрового юаня услугу печати выписок по операциям кошелька.

  3. Основатель POAP, возможно, подписался на 100 000 ETH во время ICO 2015 года.

  4. UBTECH выпускает платформу имитационного моделирования воплощённого интеллекта Thinker-Sim.

  5. Период подачи заявок на получение лицензий для поставщиков услуг виртуальных активов в Бразилии завершился: заявки подали лишь около 40 компаний.